Monday, 11 May 2015

wk:6 demolition and groundworks week 6 of 7...



Week 6 is now up and we are just embarking on Week 7. The block work of the foundations is complete for the main building. Still some work on the retaining wall (right) and terrace (currently non existent) to do. Insulation is already partly fitted, the levels have been brought up and the drains are in. There is still some service (water, power, etc in and back out to the garage) connections to be added (bottom left) . 

Tomorrow will be a big day for Team Tozer as they add various membranes and then 200mm of Celotex insulation (see below) and then the steel reinforcement before the concrete for the slab gets poured on Wednesday. Reportedly four wagon loads! 




Amazingly when we visited the site tonight at 6.45 Chris was still onsite cracking on with ensuring the compacted sub floor was just the right height all over.  


All this insulation will be installed tomorrow across the full print before being covered in 150mm of concrete.