As week 7 ended the slab was indeed down and polished.
There is still work to do though on the 7 week demolition and groundworks package though. All hands have been helping out on the retaining wall in Brendan's absence!
Prep is made for pouring the concrete slab on which the block work steps up to the terrace will sit. The concrete goes into the area on the right with the steel grid suspended on blocks.
Brendan did mange to get back to the site on Saturday and started to make good progress on the terrace wall.
The back retaining wall is pretty much complete now.
The week ahead should be an exciting one with lots of blockwork scheduled for the terrace. Then Jonathan's team start on site erecting the timber frame on Wednesday which we are very much looking forward to.