This week we have had four guys on site for much of the week which is double what we have had for some time so its been great to see the progress.
The cladding is looking really nice. Picture below from this morning. The East, North and West (pictured below) walls are probably about 60-70% complete and we hope the will be finished next week to allow Tommy and Zac to move onto the South (front) of the building and balcony area.
The apparent vertical ladder of missing (cutout) bits toward the front of the building below are the method we are using to obscure the unglazed windows in either end of the balcony.
Then two new faces have been on site.
The cladding is looking really nice. Picture below from this morning. The East, North and West (pictured below) walls are probably about 60-70% complete and we hope the will be finished next week to allow Tommy and Zac to move onto the South (front) of the building and balcony area.
The apparent vertical ladder of missing (cutout) bits toward the front of the building below are the method we are using to obscure the unglazed windows in either end of the balcony.
Then two new faces have been on site.
John (above) and Steve (below) have been inside cracking on with the plaster boarding, installing the MVHR ducting and ports, door linings, shadow gaps etc and crack on they have. With some pretty huge days they hope to have completed approximately 80 - 90% of the plaster boarding by the end of this weekend as well as the door linings, and all the MVHR ducts.
Much of the upstairs is now mostly boarded.
The downstairs is also coming on rapidly. With the boards on the walls it really helps develop a sense of the spaces which is very exciting. The big exposed oak posts are also looking really good too as they have been covered up for protection for a long time.